Generator and UPS working together
By David Otieno, Senior ICT Consultant 1 min read
The UPS bridges the seconds until the generator starts; the generator carries the long outage. Getting the hand-off right takes planning.
For sites that must keep running through long outages, a generator and UPS work as a team. Problems usually appear at the hand-off between them.
The sequence
- Mains power fails; the UPS instantly carries the load on battery.
- The generator starts and stabilises.
- An automatic transfer switch moves the supply to the generator.
- The UPS returns to mains-type operation, now fed by the generator, and recharges its batteries.
- When mains returns, the transfer switch moves back and the generator cools down and stops.
Common problems
- **Generator output not accepted by the UPS:** frequency or voltage variations can cause some UPS units to stay on battery. Online UPS units generally cope best; settings may need adjusting.
- **Undersized generator:** it must handle the UPS load plus battery recharging and any other connected loads.
- **Batteries too small:** the UPS must cover the generator's start and transfer time with margin.
Test under load
Test regularly by simulating a mains failure with real load connected, not just by starting the generator. Record the results.